Meeka reports 7,237 ounces of gold production in September quarter

Meeka reports 7,237 ounces of gold production in September quarter

Meeka Metals said gold production at the Murchison Gold Project totalled 7,237 ounces in the September 2026 quarter. The company said it would release its Quarterly Activities Report in the second half of October 2026.

Processing throughput totalled 150,000 tonnes, comprising high-grade underground ore, low-grade underground development ore and open-pit stockpiles. Metallurgical recovery averaged 95%, according to the company.

Open-pit mining ceased in July 2026 and development of Meeka's second underground mine at Turnberry commenced. The company reported cash of $51 million at 30 September 2026, compared with $38 million at 30 June 2026.

Source: Download MEK official ASX announcement, 2026-10-09.

Andy Well underground mine long-section figure from Meeka Metals' 9 October 2026 company announcement.