In its November 2026 investor presentation, Broken Hill Mines said more than 85,000 metres of drilling is to be converted into upgraded Mineral Resource Estimates for the Rasp and Pinnacles operations. The company identified an MRE update as due by the end of 2026.
The company reported a total Mineral Resource of 16.0 million tonnes, comprising 10.1 million tonnes at Rasp and 6.0 million tonnes at Pinnacles. It also outlined exploration targets at Centenary and Pinnacles, while noting that these targets are conceptual and that further exploration may not result in a Mineral Resource estimate.
Broken Hill Mines said its Rasp and Pinnacles mines feed a single processing facility at Rasp, with design capacity of 750,000 tonnes per annum. The presentation also described a tailings dewatering plant as intended to unlock latent plant capacity for the planned ramp-up.
Source: Download BHM official ASX announcement, 2026-11-27.
Pinnacles Mine historic infrastructure, from Broken Hill Mines' November 2026 investor presentation.