Theta Gold Mines reported that construction of the TGME gold plant in South Africa was 81% complete to October 2026. The company identified a Q1 2027 target for first gold pour.
The company said it issued US$90 million of senior secured bonds in June 2026 to finance development of the Transvaal Gold Mining Estates project. Theta Gold said it had completed two bond drawdowns totalling US$72.6 million, with further releases subject to construction funding needs and applicable cost-to-complete tests.
Theta Gold's base-case plan forecasts production of 871,000 ounces of gold over a 13.1-year mine life from Beta, Rietfontein, CDM, Frankfort, and reprocessing of rock dumps and tailings. The company targets annual production of 90,000 to 120,000 ounces, with a modular plant design intended to support a pathway to 160,000 ounces per year with minimal capital expenditure.
Source: Download TGM official ASX announcement, 2026-11-27.
Aerial view of the TGME project site from Theta Gold Mines' investor presentation dated 27 November 2026.