Maritana says Black Swan processing hub development remains on schedule

Maritana says Black Swan processing hub development remains on schedule

Maritana said development of the Black Swan Processing Hub, about 50km northeast of Kalgoorlie in Western Australia's Goldfields, remains on track under its existing early works agreement with GR Engineering Services. The company has targeted first gold in H2 2027, a forward-looking timetable.

The company said fabrication of the pre-leach thickener was complete and the unit was ready for shipment. Mill motors and a mill motor transformer were targeted for delivery in the December 2026 quarter, while the extended early works agreement allows engineering, procurement and construction activities to continue as the principal EPC contract is finalised.

Construction activity includes CIL tank foundations, where Civitech is releasing completed foundations for steelwork installation, and earthworks for the pre-leach thickener foundation. Maritana also reported that removal of the jaw crusher had begun ahead of refurbishment in Perth, as part of redevelopment of the front-end ore handling system.

At the ROM pad, earthworks were nearly complete, according to Maritana. The company said the revised design is intended to support a hub-and-spoke model through receipt, separate stockpiling and blending of ore from multiple regional mining operations.

Source: Download MRT official ASX announcement, 2026-11-27.

Aerial view of Black Swan Processing Hub site progress, from Maritana Minerals' 27 November 2026 company announcement.