Minbos confirmed that Kz1.97 billion, approximately US$2.2 million, was drawn under the Kz5 billion Banco de Fomento Angola construction facility on 18 November and paid directly to Soul Rock Limitada for construction contractors and suppliers.
The company said it lodged a second US$2.8 million utilisation claim with the Industrial Development Corporation of South Africa on 11 November under its existing debt facility. Minbos said that drawdown remains subject to the facility's applicable requirements.
An initial mining campaign at Cácata has been completed, producing 23,495 tonnes of phosphate rock now held in an on-site run-of-mine stockpile. Minbos said the material is intended as feedstock for commissioning of the Subantando Beneficiation Plant.
Construction fabrication in Portugal is nearing completion, and Minbos continues to target commissioning in the second quarter of 2027. The company cautioned that commissioning and other forward-looking statements are subject to risks and uncertainties, including regulatory, contractual, weather and funding risks.
Source: Download MNB official ASX announcement, 2026-11-23.
Photographs of the Subantando Beneficiation Plant from Minbos Resources’ company announcement dated 23 November 2026.