Ramelius Resources released its chair's address and managing director's presentation ahead of its 2026 annual general meeting. The company said it had delivered on operational guidance for the sixth consecutive year.
The company’s FY27-to-FY30 outlook forecasts annual gold production rising from 205,000-225,000 ounces in FY27 to 560,000-610,000 ounces in FY30. Ramelius described the Mt Magnet outlook as a production target, including a proportion of Inferred Mineral Resources, and cautioned there is no certainty the target will be realised.
Ramelius said engineering, design and refurbishment work progressed during FY26, alongside front-end engineering design for a new three-million-tonne-per-annum processing circuit. The company said it had appointed Primero as engineering, procurement and construction contractor for the circuit.
Source: Download RMS official ASX announcement, 2026-11-19.
Aerial mine-site photograph from Ramelius Resources' 19 November 2026 annual general meeting announcement.