VRX Silica said it has been granted state environmental and mining permits for its Arrowsmith silica sand project, with final amendments pending and expected in the fourth quarter of calendar 2026. The amendments relate to relocating the processing plant, infrastructure and access roads outside the originally designed mine development envelope onto adjacent farmland, which the company says would lower environmental impacts and upfront capital costs.
The company said Pareto Securities has been appointed for debt financing and that the project financing process is under way. VRX is targeting early 2028 for Arrowsmith production and first trial shipments, subject to the stated project milestones.
VRX's schedule shows approval amendments, site establishment, early works and financing completion targeted for the fourth quarter of 2026, followed by process plant construction in the first quarter of 2027, pre-strip mining in the third quarter, commissioning in the fourth quarter and trial shipments to offtake customers in the first quarter of 2028.
VRX said it has executed six binding offtake contracts covering 960,000 tonnes a year across four countries, representing about half of planned Arrowsmith production. The contracts remain subject to financing, final permitting, port access and an initial trial shipment.
Source: Download VRX official ASX announcement, 2026-11-20.