Boab said its updated Sorby Hills Project Delivery Plan extended the project mine life from 8.5 years to 10.5 years. The plan incorporated an updated Ore Reserve of 18.3 million tonnes grading 37.3 grams per tonne silver and 3.2% lead, while the life-of-mine production target was approximately 22 million tonnes containing 690,000 tonnes of lead and 26 million ounces of silver.
The company said the production target and associated financial forecasts are based partly on Inferred Mineral Resources. It cautioned that Inferred Resources have a low level of geological confidence and there is no certainty that further work will convert them to Indicated Resources or that the production target will be realised.
During the quarter, Boab reported that its updated Mineral Resource Estimate increased to 50.6 million tonnes grading 3.0% lead, 34 grams per tonne silver and 0.4% zinc, a 7% increase in tonnage from the 2021 estimate. The company attributed the increase in part to infill drilling and the use of net smelter return modelling.
Boab executed a binding heads of agreement with RE:GROUP Australia for mining services at Sorby Hills. Site establishment activities are scheduled to begin in January 2027 and mining services are planned to start no later than March 2027, while the definitive contract is expected to be executed in the December 2026 quarter.
Construction advanced at Sorby Hills, including concrete works in the primary crushing, mill, flotation and coarse ore bin areas. Boab also reported progress on bulk earthworks and the evaporation pond, while stage two of the accommodation village was nearing completion, taking camp capacity to 132 rooms.
Source: Download BML official ASX announcement, 2026-10-27.
Mill foundations at Sorby Hills, from Boab Metals' ASX announcement dated 27 October 2026.