Cyprium reports heap leach commissioning milestones at Nifty

Cyprium reports heap leach commissioning milestones at Nifty

The company said all infrastructure needed to support leaching from the ILS and PLS ponds had been constructed and was in commissioning. Leaching solution was being delivered to Blocks 1 and 3, with activities ramping toward continuous injection as additional wells are activated.

Cyprium said target direct-injection rates and volumes had been achieved in the initial Block 1 area, while monitoring-well flows supported its assessment that the existing Nifty heap has sufficient permeability and connectivity for direct-injection leaching.

The company said high-voltage power had been connected to SXEW electrical infrastructure and controls. It said pre-commissioning was accelerating and first copper cathode production remained on track for the fourth quarter of 2026.

Source: Download CYM official ASX announcement, 2026-10-09.

Cyprium Metals’ 9 October 2026 company announcement shows high-pressure injection leaching equipment at Nifty.