Bannerman reports Etango early works progress ahead of targeted FID

Bannerman reports Etango early works progress ahead of targeted FID

Bannerman Energy reported that the bulk earthworks package at Etango is about 99% complete. The company expects Phase 4, focused on process solution ponds and wet plant terraces, to be completed during December.

The company said approximately 50% of the required heap leach drainage aggregate had been produced by local contractor Tulela Mining & Construction and was being built into inventory for future placement in the heap leach pad drainage system.

About 14,700 cubic metres of concrete has been cast across the Phase 1 and Phase 2A packages, representing approximately 86% of planned concrete volume for those phases, Bannerman said.

Bannerman said it was making final preparations for a targeted Etango final investment decision during Q4 2026 following completion of the CNOL strategic investment and joint venture transaction. The company said full-scale construction is intended to follow promptly after FID.

Etango recorded its first lost-time injury of the project on 2 September, Bannerman said. A contractor employee sustained a hairline fracture to his left foot while operating a compactor and received medical attention.

Source: Download BMN official ASX announcement, 2026-09-29.