BCM advances Ema rare earth project development activities

BCM advances Ema rare earth project development activities

BCM said INCRA Amazonas has approved a land-access agreement for proposed activities on INCRA-controlled land and issued a certificate confirming no impediment to environmental licensing continuing. Final ratification of the land-access agreement by INCRA in Brasília remains outstanding.

The company said final exploration reports for both Ema tenements have been approved by Brazil’s National Mining Agency. Development environmental licensing with IPAAM and two trial mining licence applications remain pending.

BCM said it remains in discussions with selected prospective offtakers regarding product specifications, development timing and potential supply arrangements. It said funding discussions are also under way with interested parties in Brazil and North America, while no offtake agreements have been executed.

Altris Engineering is leading the project’s front-end engineering and design program, according to BCM. The company said it is selecting a Brazilian engineering partner to refine plant and infrastructure design, confirm equipment selections and update capital estimates and the project schedule.

BCM said Ema is being developed using in-situ recovery, with magnesium sulphate solution intended to recover rare earth elements from mineralised clay. The recovered material is planned to be processed into mixed rare earth carbonate for export and downstream refining.

Source: Download BCM official ASX announcement, 2026-11-26.