Viridis said its definitive feasibility study evaluates a 5 million-tonne-per-year mining and processing operation at Colossus over a 25-year production target, underpinned by Ore Reserves. The company said the DFS incorporates additional engineering definition, market-tested capital and operating costs, increased geological confidence and a refining circuit intended to produce a higher-value MREC product.
Under its DFS spot-price case, Viridis projects an after-tax net present value of US$1.196 billion, an after-tax internal rate of return of 36.4% and capital payback within 2.7 years of first production. The company estimated initial development capital at US$449 million, including contingency, and said the development schedule targets first production in the second half of 2028.
During the quarter, Viridis selected Sedgman and Blossom as preferred EPCM partners and approved up to US$3 million of pre-FID expenditure. The company also placed a purchase order for a residue pressure-filtration package sized for the planned processing facility; the order includes a contractual hold point before full notice to proceed following FID.
Viridis said the Northern Concessions Preliminary Licence had been granted, while approval of its Installation Licence application remains a key construction requirement. It added that further approvals would be required for operations and later development of the Southern Complex.
Source: Download VMM official ASX announcement, 2026-10-27.