During the September quarter, Minerals 260 said it secured $420 million before costs in new funding for the Bullabulling Gold Project, comprising an additional $170 million royalty with Franco-Nevada and a $250 million two-tranche equity placement.
The company said the definitive feasibility study is on track for the first quarter of calendar 2027 to support a final investment decision. It said geotechnical testwork was complete and is expected to support improved fresh-rock pit wall angles relative to the pre-feasibility study, while metallurgical testwork continued to support PFS comminution and recovery assumptions.
Minerals 260 said construction of the Bullabulling village began in May 2026. Manufacturing of central facilities is complete, with delivery, placement and complexing underway. The company also said its board approved a further 200 rooms, taking planned village capacity to 600 rooms, with the expansion scheduled for operation by March 2027.
The company completed an initial 10m by 10m grade-control drilling program across the Phoenix North and South areas, comprising 320 reverse-circulation holes for 25,970m. It said preliminary analysis indicated grades and mineralised intercepts correlated well with drilling underpinning the mineral resource estimate, while further drilling is planned to assess higher-grade zones at Bacchus.
Minerals 260 said all remaining documents required for approvals ahead of construction had been submitted and applications were under assessment. The company reported cash and short-term deposits of about $530 million at September 30, 2026.
Source: Download MI6 official ASX announcement, 2026-10-27.
Aerial view of Bullabulling village construction progress, from Minerals 260's 27 October 2026 company announcement.