Underground development at West Wits Mining's Qala Shallows project reached 1,150 metres by 30 September 2026, comprising 513 metres of on-reef development and 637 metres of waste development. Monthly advance increased from 73 metres in July to 183 metres in August and 200 metres in September.
The company said 112 ounces of gold were recovered during the quarter from on-reef development ore toll-treated at Sibanye-Stillwater's Ezulwini plant. It said historic 2 Level stoping areas were being prepared for trackless equipment, with primary stoping scheduled to begin in February 2027.
Surface infrastructure was 61% complete at quarter end, compared with 45% at 30 June 2026. The haulage road had been completed and handed over, while the pollution control dam and permanent ore handling facility were at advanced stages; the company said critical surface infrastructure remained on track for completion in the third quarter of 2027.
Subsequent to the reporting period, West Wits received a R236 million second drawdown under its senior loan facility after meeting lender conditions. The company said the facility fully funds Qala Shallows through to its stated steady-state target, while noting this is based on its 2025 definitive feasibility study.
Source: Download WWI official ASX announcement, 2026-10-27.
West Wits Mining photograph of development drilling and survey at an underground face at Qala Shallows, published in its 27 October 2026 announcement.