Rox reports 39% completion at Youanmi processing plant

Rox reports 39% completion at Youanmi processing plant

Rox said the 1.0Mtpa Youanmi Processing Plant was 39% complete after civil, structural and mechanical work progressed during September. The company said tank installation was continuing to schedule and remaining long-lead items were under construction or in transit.

The company reported 566 metres of underground development advance during September. At United North, Rox said the first two levels were complete and drilling of the first production stopes was on track to start in mid-October following ladderway and ventilation work.

Rox said it achieved financial close on $350 million of debt facilities on 5 October and made an initial $90.2 million drawdown under the project term loan. It reported cash of $149.2 million following the drawdown.

Source: Download RXL official ASX announcement, 2026-10-12.

Aerial view of construction progress at the Youanmi processing plant, from Rox Resources' 12 October 2026 company announcement.