Toubani targets first gold from Kobada in Q3 2027

Toubani targets first gold from Kobada in Q3 2027

Toubani reported that process plant construction was well advanced, with all contractors mobilised and more than 900 personnel on site across multiple disciplines. The company said Kobada reached 1 million lost-time-injury-free man-hours in September.

Structural steel fabrication for the process plant had reached 80%, while process plant engineering was more than 95% complete. Power plant engineering was 80% complete, and excavation work on site was nearing completion, according to the company.

The company said an updated Kobada mineral resource estimate, incorporating about 26,000 metres of new drilling, was being prepared by Entech Pty Ltd. Toubani expects the update to support final mine planning, pit design and scheduling before mining is planned to begin in early 2027.

During the quarter, Toubani completed an entitlement offer that raised approximately A$70 million before costs. The company said its funding package, gold stream and existing cash were intended to support Kobada development, with first gold targeted for the third quarter of 2027.

Source: Download TRE official ASX announcement, 2026-10-28.

CIL tank construction at the Kobada Gold Project, from Toubani Resources' 28 October 2026 quarterly activities announcement.