DBI completes SL1A shiploader replacement at Dalrymple Bay Terminal

DBI completes SL1A shiploader replacement at Dalrymple Bay Terminal

Dalrymple Bay Infrastructure Limited released an investor presentation for a Dalrymple Bay Terminal site visit scheduled for 25 November 2026.

DBI said the new SL1A shiploader replaced the 43-year-old SL1 asset. The project began in April 2023, had a budget of $165.4 million excluding interest during construction, and was completed on 14 November 2026 on time and on budget. Commissioning began on 17 October, first coal occurred on 12 November, and the asset was handed to operations on 14 November.

The company said it is also replacing the 43-year-old SR2 stacker reclaimer with RL4. Construction was due to be completed by the end of November 2026, with handover into operation expected in January 2027 and SR2 removal targeted for April 2027.

Source: Download DBI official ASX announcement, 2026-11-25.

Dalrymple Bay Infrastructure photograph from its 24 November 2026 investor presentation announcement.