Bellevue Gold has outlined FY27 guidance for production of 150,000 to 170,000 ounces, all-in sustaining costs of A$2,800 to A$3,100 per ounce, growth capital expenditure of A$90 million to A$100 million and an exploration budget of A$25 million to A$30 million.
The company said five established mining fronts were intended to support higher and more consistent production during FY27. Its operating plan includes an underground contractor changeover in the first quarter, spending most growth capital in the first half, and commissioning the paste fill plant in the third quarter.
Bellevue said mine designs across its five established mining areas extend to about 2035. The company reported a total Ore Reserve of 6.8 million tonnes grading 4.5 grams per tonne gold for 1.0 million ounces.
Source: Download BGL official ASX announcement, 2026-11-09.
Bellevue Gold processing plant photograph from the company’s UBS Mining Conference presentation, November 2026.