21 May 2025 | Alstonville, NSW – Polymetals Resources (ASX:POL) has confirmed that redevelopment of its Endeavor Silver-Zinc Mine is progressing on schedule and within budget, with commissioning well underway and first cash flow expected in June.
Following the completion of major site works and infrastructure upgrades, the site has entered full commissioning. Crushed ore is being hoisted and stockpiled, with wet commissioning of the plant in progress and ore processing scheduled to begin next week.
Key highlights:
-
First ore crushed and hoisted to surface
-
Over 40,000 tonnes of ore stockpiled underground
-
Site targeting 65,000t/month processing rate in H2 2025